Material Requirments Planning (MRP) using Fixed Order Quantity

preview_player
Показать описание
Material Requirments Planning (MRP) using Fixed Order Quantity
Рекомендации по теме
Комментарии
Автор

What I spent hours trying to figure out you helped me solve in 5:09... Thank you!!

lukeoneill
Автор

Thank you for doing what my college professor is supposed to be doing, the least he could have done was provide us with the link.

alannabors
Автор

I have my exam today and you saved me... Thanks a ton!!!❤️

avani-verma
Автор

Am going to share to my students and am sure they will get the concept better.

solomonwakjira
Автор

We got PhD professor that enjoy making this difficult.
Thank you for the video!

rolandn
Автор

you are just awesome banging my head viewing other tutorial cant get, but in your video it directly go into my head, thanks a lot

syedsafdar
Автор

thanks ... for your explain.... short and best...

malithpriyankara
Автор

This was a great explanation thank you

Raddy_N
Автор

Develop an MRP record, similar to the one in Figure 4-17, for wheat germ for the five
weeks of January. Wheat germ must be ordered in bulk-container quantities, so the
planned orders must be in multiples of 2, 000 pounds. Use a lead time of one week and an
initial on-hand inventory of 3, 184 pounds; assume that an order of 8, 000 pounds is
scheduled for receipt during Week 1. Are there any weeks when you, as a planner, would
consider placing an order above or below the minimum required? Why? (Assume that
there are no problems with storage capacity or shelf life.)

aqibshafique
Автор

where is the calculation for child B and C ?

shipride_digisolutions
Автор

do you remember you said fixed order quantity is 80 when you ordered more than 80 in period 5 and 7 ?

evrardondonguema
Автор

May i know does FOQ mean lot sizing? Thanks

TheChow
Автор

Can u put the teks of English bcs more understand when the teks here

wayanwidya