Giga Berlin | 2022-09-17 | Construction update

Показать описание
A new tent is getting built on the area south of the Drive Unit Building (6:00) while production was running this Saturday at Tesla's Gigafactory Berlin-Brandenburg.
Holes in the walls of the cell production building, which have been used bring in equipment, are getting closed (6:55) and the cooling units on the roof are getting connected (10:30).
The shuttle train will run on tracks next to the retention wall (9:15) to a new train station (9:40, 13:45 on right side).
The first section of the main road is getting dismantled (9:44) and the side road got a layer of gravel (9:50, 12:52).
Construction of the next parking lot section is progressing (14:05), street lights have been errected (14:36) and foundations with an unknown purpose are getting built (15:00).
At the casting section the walls that have been opened are getting closed with air vent panels and a foundation (probably for tanks) is getting built in front of it (17:02, 17:32).
After a long time, the pile driver for the square piles started working again and placed a lot of piles this week at the extension of the stamping section (19:05) while the first foundation section is getting ready for rebar (19:15).
All cooling units at the central utility building seem to be connected now (22:00) and an underground tank is placed near the waste water treatment (23:00 top right).
The fire station will get an electric fire truck soon, but it didn't arrive yet (23:13). Construction on the future recycling area started with a layer of gravel (24:05). Castings, battery pack boxes and aluminum bars are stored at the distribution area (25:33) and Model Ys are getting loaded onto trucks (27:25).
If you want to support me:
Bitcoin: bc1qdl63dswrepe25hdh86wlktmrhcm29t3zyqa8k2
Follow me on Twitter for the latest updates:
See all my photos from Giga Berlin:
For videos from Giga Shanghai I recommend the channel of Wuwa (乌瓦):
Music in this Video:
#tesla #gigafactory #gigaberlin
Holes in the walls of the cell production building, which have been used bring in equipment, are getting closed (6:55) and the cooling units on the roof are getting connected (10:30).
The shuttle train will run on tracks next to the retention wall (9:15) to a new train station (9:40, 13:45 on right side).
The first section of the main road is getting dismantled (9:44) and the side road got a layer of gravel (9:50, 12:52).
Construction of the next parking lot section is progressing (14:05), street lights have been errected (14:36) and foundations with an unknown purpose are getting built (15:00).
At the casting section the walls that have been opened are getting closed with air vent panels and a foundation (probably for tanks) is getting built in front of it (17:02, 17:32).
After a long time, the pile driver for the square piles started working again and placed a lot of piles this week at the extension of the stamping section (19:05) while the first foundation section is getting ready for rebar (19:15).
All cooling units at the central utility building seem to be connected now (22:00) and an underground tank is placed near the waste water treatment (23:00 top right).
The fire station will get an electric fire truck soon, but it didn't arrive yet (23:13). Construction on the future recycling area started with a layer of gravel (24:05). Castings, battery pack boxes and aluminum bars are stored at the distribution area (25:33) and Model Ys are getting loaded onto trucks (27:25).
If you want to support me:
Bitcoin: bc1qdl63dswrepe25hdh86wlktmrhcm29t3zyqa8k2
Follow me on Twitter for the latest updates:
See all my photos from Giga Berlin:
For videos from Giga Shanghai I recommend the channel of Wuwa (乌瓦):
Music in this Video:
#tesla #gigafactory #gigaberlin
Комментарии