Operations Management: Capacity Mangement – Effective Capacity
![preview_player](https://i.ytimg.com/vi/KLK-0_18FMI/maxresdefault.jpg)
Показать описание
This problem walk-though video will demonstrate how to calculate the effective capacity of a factory and determine how much extra capacity is required to meet expected demand.
CLARIFICATION: At 0:24 the 230 working days is calculated as 250 working days – 20 maintenance days = 30 days available for production.
CORRECTION: At 1:25 the calculation (and audio) incorrectly shows 22,080 × 60 min/hour × 24 min/unit. The formula should divide by 24 min/unit as follows:
22,080 machine hours × 60 min/hour ÷ 24 min/unit
CLARIFICATION: At 0:24 the 230 working days is calculated as 250 working days – 20 maintenance days = 30 days available for production.
CORRECTION: At 1:25 the calculation (and audio) incorrectly shows 22,080 × 60 min/hour × 24 min/unit. The formula should divide by 24 min/unit as follows:
22,080 machine hours × 60 min/hour ÷ 24 min/unit
Operations Management: Capacity Mangement – Effective Capacity
Operations Management: Capacity Management – Utilization and Efficiency
Design Capacity and Effective Capacity - Calculating Capacity Utilization and Efficiency Rate
Operations Management Ch5 part 1
Operations Management: Single-Factor & Multi-Factor Productivity
Lecture 29 Capacity Planning: Introduction
Introduction to Operations Management | IIMBx on edX
What is Operations Management? | Rowtons Training by Laurence Gartside
Operations Managment Lecture 01C
Operations Management: Aggregate Planning – Chase Strategy
Capacity and Constraint Management Ch7 Supplement Part I
IB Business and Management: Operations Mangement: - 5.7 Production Planning
TMC 410 Enterprise Operations: Total Quality Managment-5
For pharma college Accoununting & Management Oprational Managment 3rd year students Chapter 3 P...
Operations & Supply Chain Management: Scheduling
Why Middle Management is the Hardest Job | Simon Sinek
How Toyota Changed The Way We Make Things
Should you Balance Capacity with Demand? | Rowtons Training by Laurence Gartside
Operations Layout: Assembly Line Balancing II
Material Requirments Planning (MRP) using Fixed Order Quantity
Chapter 1: Operations & Productivity
For pharma college Accoununting & Management Oprational Managment 3rd year students Chapter 1 P...
Factors Influencing Effective Capacity - Forecasting, Aggregate Planning, Capacity Planning
Building Managment Capacity - Lessons Learned
Комментарии