Situation based questions for PMP® Exam | Episode 11 | Practice questions for PMP® Exam preparation

preview_player
Показать описание
In this video, we have solved situational questions on Closing process with detailed explanation for every question that will help solve not only these type of questions but numerous others that test similar skillsets.

00:00 Intro
00:45 Question 1
09:37 Question 2
36:14 Question 3
39:59 Question 4
47:40 Question 5

___________

👍 Like, Comment, and Share this video if you found it helpful!

Useful Links:

📢 Connect with Us:

📧 Contact Us:
Phone/WhatsApp/Telegram: +91 9673332684

🔔 Subscribe for more updates and tips!

If you have any questions or need further guidance, feel free to leave a comment below. Good luck with your PMP® preparation!

#pmpexamprep #pmp2024 #projectmanagement #projectmanagementtools #pmpexamprep #pmpexamtips #pmpexamprep #pmpcertifications #pmpcertification #pmp
Рекомендации по теме
Комментарии
Автор

Amit, Excellent Logic explained in Question 2 to compare Validation of the scope and stakeholders Concensus

SailuIVA
Автор

Finally a video dedicated to project closure. Thank you! Scored 4 out of 5. Rationale behind question No 2 was clear.

muttoon
Автор

for Q-3, the gathering of feedback from stakeholders and team members happen during closure phase also. The stakeholder can be the project sponsor, unless they accept the verified and validated deliverables <o/p of monitoring and controlling PG >, we can not deem the project is ready to be closed. please explain on this

meeraraina
Автор

I’ve been looking for videos on project closure. Thanks a ton for this one Amit!

azraabbas
Автор

Hi Amit
Question -2
A- tells about adding additional cost in terms of external auditor,
B- since the project is in closing stage that means all the efforts are made to meet the final result throughout the project duration, that means the closing criteria as mentioned in the project charter. Can we keep on updating the charter then How we will close the project?
C- reaching consensus by bringing 2 stakeholders on one table is better, because I am not going to spend extra cost for that. Also the conflict arised in the closing stage so making consensus shall not be planning stage activity.
D - is ruled out

I am not convinced by the answer A.
My answer is C, can you please tell why C is not the answer.

rizwanshahab
Автор

In Question 4 - Why I not choose option for external auditor is because we already have too much cost overruns and while bringing external auditor will also consume more amount so I rejected this...

azharbashir
Автор

Sir my view option B is also fit as criteria is fixed in Project charter

yashpalchudasama
Автор

regarding question 5, I donot agree that we can add something new to the proect during the closing, It should have been rejected,

adrianoFB