How To Update Progress In Primavera P6 || Update Project Schedule in 2020 || [Latest Primavera P6]

preview_player
Показать описание
In this tutorial, let us learn How to update progress In Primavera P6

So, let us open a sample project and set the layout to show like this with 4 compulsory columns Start, Finish, Baseline Start and Baseline Finish.

There are 2 ways to update any project schedule. One is updating manually and other automatically using the update progress built in option, which is present in the tools tab.

Remember friends, you need to use this update progress feature only when you project is going exactly as per the baseline plan. If not, you should be using the manual method only.

Let us select this activity, chemical dosing plant whose start date is 4th Jun’20 and go to tools and click on update progress.

You will get the update progress dialog box like this, with different options to select.

It is asking whether all the highlighted activities to be updated or selected activities only.

You can change the data date here. Let me put 5th Jun’20.
Then it will automatically highlight all those activities falling before 5th Jun (which is nothing but the spotlight feature).

You can click on Apply button, so as to update automatically.

Now, let me select the 2nd option to update only the selected activity only.
Click Apply button and you can observe that the start date 4th June has been considered as Actual start date and the % progress of the activity has also been changed accordingly.

But, it is suggested that we should not be using this method when our schedule is not following the exact baseline plan.

So, the ideal method is to update manually, like for example the activity Equipment move in skids is supposed to be started on 26th June, suppose it has started on 15th Jun’20 and I update it manually like this, go to details, go to status tab and check the start checkbox and enter the date as 15th Jun’20, enter the %progress.

If I would have run the automatic way, the start date would have been the baseline date but not the earlier date.

Ok friends, in this way you need to update all the activities manually and then schedule the project to see the overall impact and can compare this with the baseline plan.

So friends, this is all about How to update progress in Primavera P6.

If you have enjoyed this tutorial, please give me a like, share and comment.
For further more interesting videos, please do subscribe dptutorials

If you found this video valuable, give it a like. If you know someone who needs to see it, share it. Leave a comment below with your thoughts. Add it to a playlist if you want to watch it later.

***********************************************

Tools for youtube vlogging:

Note: This description contains affiliate links, which means at no additional cost to you, we will receive a small commission if you make a purchase using the links. This helps support the channel and allows us to continue to make videos like this. Thank you for your support!

***********************************************

You Can Connect with Me at:

Follow:

#dptutorials #Update progress in Primavera #Primavera Free #Primavera tricks

Tags: -

P6:
primavera p6 training online, primavera p6, primavera p6 training, primavera p6 tutorial, oracle primavera, primavera p6 download, primavera 6, oracle primavera p6, primavera p6 free download, primavera project management, primavera project planner, primavera download
Рекомендации по теме
Комментарии
Автор

Let's suppose we don't remember the actual start date of the activity 'Equipment move in skids'. The activity was to finish by 8 July but didn't finish by the BL finish date. Today is 10 July and we know that the said activity is 70 % complete. Can we got to % Activity Complete column and directly write 70% and schedule then? Will it be right thing to do?

diverzzz.
Автор

I enjoined having tutorial with you but i wanna have a further tutorial on how to revised a schedule, updating it every week or two and calculation of progress quantities .

ejiroohwodiasa
Автор

In general tab
What should be duration types. You selected "Fixed duration and unit/time".
If I select "Fixed duration and unit" how it would be different.?

praveengarg
Автор

Sir,

This is Mahesh. Please advise how to update the progress month wise.

For example. Blasting 3000sqm

Budget units

January - 1000

February - 1000

March - 1000


But

Actual

January - 500

February - 450

March - 690


I updated January month. How to update Feb month progress sir

mahesht
Автор

please tell in detail first how to add the dates in bl start and bl finish .i cannot change the dates of bl start and bl finish manually without disturbing the start and finish dates also cannot change the percentage.

Amblog
Автор

Would u please explain how to make variance between 2 updates global changes

muhamedessawy
Автор

Great video
Question, How to do or show the KPI in Primavera P6?

nazirahmad
Автор

Hello Sir, while updating dates of activity as soon as I press F9, the dates I entered are changing. How do I fix this to enter the desired dates and save them?
Kindly answer.

mohammedmansoor
Автор

Thanks for the video,
Could you please make video for to update the p6 using the update from excel file thru Export & Import method.I ave tried the same but some error coming.

muhammedmuhsin
Автор

How does SOW and SOV impacts on Primavera P6 Schedule? Kindly advise!
Do you have any forum, where we can post our Questions?

nazirahmad
Автор

Can you share your insights on how to report project overall progress in P6 along with S-Curve rather than the excel based EVM / DCI files. Thanks for this video !

nishajoseph
Автор

My question is - Suppose I have to update the schedule for the month of Nov 2020, and the last update was with the data date of Oct 2020, so is the procedure that I first actualize, what has been attained in Nov and then move the data date to Nov 2020. Is this the correct procedure? Can you please explain this.

nishajoseph
Автор

My question is While updating the schedule we will take the Last week updated Schedule and Update this week. So, why we will not take approved baseline for updating?? Why we take the last week Schedukle??

MUsman-viif
Автор

Very educative video but the Physical % column does not roll-up, is it ok to use performance % complete to display the physical % complete. Thanks

benoevabeta
Автор

Nice Information Sir but can it be explained in Hindi language also?

Ravi_
Автор

my dear with this we can not change %age

Amblog
Автор

Could you share this schedule with me I can give you my email please

mubaidq