CREATE 6 DAY X 10 HOUR, & 4 DAY X 10 HOUR WORK CALENDARS IN MS PROJECT, NO. 41 MS PROJECT MADE EASY

preview_player
Показать описание
Common calendars often require setting a 6 day work week or a 4 day work week with varying hours. In this video I go through the process of setting this up along with some of the possible pitfalls in how MS Project may behave when changing the calendar after task duration and inputs have already been made.
If you wish to see the other videos in this series review my playlists on my channel, click subscribe and the notification icon. If you have questions leave them in the comments section and have a wonderful day!
Other Videos in the series (More listed under the playlist)

Tom Stephenson is a national award-winning professor (George Brown College, University of Toronto) and best-selling author whose background in education spans nearly three decades. His diverse teaching disciplines include construction project management, business management, human resource management, architecture, carpentry, and brick and stone masonry. As a dual-professional, Tom is called upon by industry leaders to translate knowledge, reinvigorate corporate culture, and inspire innovation in emerging and established companies across Canada. Before breaking into the academic realm, Tom acquired more than a decade of practical project-management experience, operating a mid-sized Toronto-based general contracting firm. He is also the author of the newly released Planning, Scheduling, and Control of Construction Projects with American Technical Publishers and the four best-selling editions of Understanding Construction Drawings for Housing and Small Buildings with Nelson Publishing Canada. Tom most recently received the Toronto Construction Association’s 2020 Chancellor’s Award for “helping his peers become more ethical, knowledgeable and professional.” A champion of change management, Tom takes pride in helping students and businesses navigate uncharted territories, take calculated risks and rise above the status quo. Some of the companies he’s worked with include Mattamy Homes, EllisDon, BIRD Construction, MCA, Maple Reinders, and Tucker HiRise, University of Toronto Project Managers.
Рекомендации по теме
Комментарии
Автор

Thank you for your help! Excellent video.

gargyboi
Автор

How to change working time half way the project, e.g working more hours without changing the timelines on the completed tasks

tafaradziva
Автор

How do I set up a 7 days a week with two 12 hr shifts?

jonheil
Автор

I hate this program sometimes!!! 16 minutes to explain this!!!! ARGH!

WECD