Project Engineer Reviewer Part 1 - 4 with answer Reference

preview_player
Показать описание
1. What Department Order speaks of the Guidelines on the Accreditation of the Contractors' and Consultants' Project Engineers to ensure that only qualified and competent project engineers will be assigned by the contractors and consultants in DPWH projects?
a) DO 01 s2019
b) DO 21 s2019
c) DO 10 s2019
d) DO 11 s2019

2. The procuring entity shall, upon a written request of the contractor which shall be submitted as a contract document, make an advance payment to the contractor in an amount not exceeding blank percent of the total contract price?
a) 5 %
b) 10 %
c) 20 %
d) 15 %

3. The advance payment shall be repaid by the contractor by deducting fifteen percent from his payments on
a) Final billing
b) First progress billing
c) Periodic progress billing
d) Quarterly billing

4. How many times does the contractor may submit a statement of work accomplished or progress billing and corresponding request for progress payment for work accomplished?
a) Once a month
b) Twice a month
c) Once a year
d) Twice a year

5. Progress payments are subject to retention of ten percent referred to as the:
a) Retention Charges
b) Retention money
c) Recoupment
d) Insurance

6. Retention shall be based on the total amount due to the contractor prior to any deduction and shall be retained from every progress payment until fifty percent of the value of works. If, after fifty percent completion, the work is satisfactorily done and on schedule, no additional retention shall be made; otherwise, the ten percent retention shall be imposed.
a) True
b) False

7. This is issued by the procuring entity to cover any increase/decrease in quantities, including the introduction of new work items that are not included in the original contract.
a) Variation Orders
b) Supplementary Letter
c) Job Order
d) Work Request

8. May be issued by the implementing official to cover any increase/decrease in quantities of original work items in the contract.
a) Job Order
b) Extra Work Order
c) Change Order
d) Work Instruction
9. May be issued by the implementing official to cover the introduction of new work necessary for the completion, improvement or protection of the project which was not included as items of work in the original contract.
a) Job Order
b) Extra Work Order
c) Change Order
d) Work Instruction

10. Variation Order does not exceed blank percent of the original contract price. Any cumulative positive Variation Order beyond this shall be subject of another contract.
a) 5 %
b) 10 %
c) 15 %
d) 20 %

11. An amount equal to one-tenth of one percent of the cost of the unperformed portion of the works for every day of delay.
a) Retention Money
b) Liquidated Damages
c) Security Bond
d) Performance Bond

12. Total sum of liquidated damages shall not exceed blank percent of the total contract price, in which event the procuring entity concerned may rescind the contract.
a) 15 %
b) 10 %
c) 20 %
d) 5 %

13. Is a written order issued to by DPWH Project Engineer to suspend the contract work wholly or partly for such period?
a) Change order
b) Variation order
c) Work suspension order
d) Contract time extension

14. Issued instead of Work Suspension Order if suspension / unworkable days is due to unfavorable weather condition (Rainy), weather disturbances or its effect (river swelling, storm surge, etc.), or other conditions rendering the site unworkable occur intermittently.
a) Change order
b) Monthly time suspension report
c) Work suspension order
d) Contract time extension

15. The contractor shall have the right to suspend work operation on any or all projects activities along the critical path of activities due to the following:

A. There exist right-of-way problems which prohibit the contractor from performing work in accordance with the approved construction schedule.
B. Requisite construction plans which must be owner-furnished are not issued to the contractor precluding any work called for by such plans.
C. Peace and order conditions make it extremely dangerous, if not possible, to work. However, this condition must be certified in writing by the Philippine National Police station which has responsibility over the affected area and confirmed by the Department of Interior and Local Government Regional Director.
D. There is failure on the part of the procuring entity to deliver government furnished materials and equipment as stipulated in the contract.
E. Delay in the payment of contractor's claim for progress billing beyond forty-five calendar days from the time the contractor's claim has been certified to by the procuring entity’s authorized representative that the documents are complete unless there are justifiable reasons thereof which shall be communicated in writing to the contractor.

a) A & B
b) C & D
c) E
d) All of the above

ANSWERS
1. C
2. D
3. C
4. A
5. B
6. A
7. A
8. C
9. B
10. B
11. B
12. B
13. C
14. B
15. D

#Project Engineer Reviewer
#Materials Engineer Reviewer
#Department of Public Works and Highways
#To God be the Glory
Рекомендации по теме
Комментарии
Автор

pdf copy available for free (for subscribers). Just comment your request and email address to where I can send the soft copy.

engineeringcivilintegrity
Автор

Thank you Sir, for your free resources. ME 1 na po ako🙏
More power po and God bless

monethmirano
Автор

Good evening sir, can I ask a pdf file for this?.. thank you

ma.jesalynsanorjo
Автор

Question #19 po dpo ba narevise na po to? Naging regional director na po?

kjvargas
Автор

sir, good morning. can i request for pdf file.. thank you

mclucenecio
Автор

Good day…can I have the pdf copy of this ?thanks

janreysumbang
Автор

Hi sir, can I request a pdf copy of the review? Thank you

khristiancaya
Автор

Hello, can I have a softcopy po of your presentation?

joshuabryantlaolapinig
Автор

Naghahanap ng ME II ang contractors ng DPWH NORTH MANILA, baka ho interesado kyo

joshlp
Автор

Good morning engr, requesting a copy sana thank you sir!

cjherome
Автор

Can I get pdf copy? Thank you so much

JohannaMarieParaso
Автор

Hi! Sir can I request for the pdf copy of the reviewer?

Thank you.

reymondigaya
Автор

Good day sir., can i have a pdf copy.of this?

abbynabuya
Автор

Hello, can i request a copy of pdf? Thanks

aileenpadilla
Автор

Good eve po, Engr. Pede pong humingi ng pdf copy po? Salamat po

kailahgupo
Автор

More upload sir P.E question . Preparation for july 1, 2023

sidracho
Автор

Good afternoon po! Pwede po makahingi ng Soft Copy? Salamat.

FaisalGani-kpnr
Автор

Good Evening sir, can i have a pdf copy of this?Thank you po.please 😀 😊

franchescavillafuerte
Автор

pahingi po sir ng pdf file. maraming salamat. more power to u

joshuacalanao
Автор

Good Morning po. Can I have the PDF file copy. Student here😁

richardkentburton