A, B, C can complete a work in 2 days. if A does the job alone in 6 days and B in 5 days. how long

preview_player
Показать описание
A, B, C can complete a work in 2 days. if A does the job alone in 6 days and B in 5 days. how long will it take for C to finish the job alone.