How to configure Work Center formula in SAP PP

preview_player
Показать описание
In this video, I present step by step guidance to configure new work center formula in SAP PP(production planning).
These formulas will be used in costing, scheduling & capacity planning.

SPRO Path-
Production - Basic Data - Work Center - Costing - Work Center Formulas
Рекомендации по теме
Комментарии
Автор

Thanks a lot sir.
I could not understand this formulas during my actual training time. But understood it here very well. Hats off to you.

ZEESHANUSTAD
Автор

Thanks for giving brief about work center formula, 🌻💐💐

syedtaseerkhadri
Автор

Great explanation...and thank you so much

தமிழ்வாழ்க-ழஞ
Автор

Hir sir your explanation is very good i have issue i hope you will clear, actually 2 work centers are there 2 work centers control by one Labor so how to split labor time each work center and also cost coming wrong can you tell me how to make formula.
Thanks for advance

amarendragoud
Автор

Hello
I see (6.21 time ) base quantity as 1 and how did you consider as10. Please let me know I am confused. Thanks in advance

yv
Автор

Hello sir! Tell me pls where is "Operation Quantity" field in Routing?

bondjames