📣 Solidus Ai Tech Data Center – Weekly Update!
This week marked significant advancements at the HPC Data Center site, aligning with our strategic goals of enhancing operational efficiency and sustainability. Here’s an overview of the latest developments:
1. Electrical Systems Finalized: The electrical works have been completed, with high-voltage testing scheduled to commence on Monday. These tests are crucial for ensuring the reliability and safety of the infrastructure.
2. CO2 Fire Suppression System Update: The control panel for the CO2 system has been installed, and the cylinders with gas are expected to arrive next week, bringing us closer to finalizing the fire safety measures.
3. Cabinet Installation Preparation: The server cabinets are prepped for installation. After the high-voltage tests are completed, the cabinets will be moved into the server room, allowing the next phase of the setup to proceed.
These updates reinforce our commitment to providing a state-of-the-art, eco-friendly HPC data center that supports diverse industries and advances European technological independence. We’re on track to meet our goals and look forward to sharing more progress in the coming weeks.
Our intelligence is more than artificial 🚀
#datacenter #2025 #artificialintelligence #ai #crypto #Solidus #Aitech #solidusaitech #cryptocurrency #bitcoin #blockchain #ethereum #investment #utilitytoken #AIaaS #BaaS #IaaS #ai #partnership #web3 #certik
This week marked significant advancements at the HPC Data Center site, aligning with our strategic goals of enhancing operational efficiency and sustainability. Here’s an overview of the latest developments:
1. Electrical Systems Finalized: The electrical works have been completed, with high-voltage testing scheduled to commence on Monday. These tests are crucial for ensuring the reliability and safety of the infrastructure.
2. CO2 Fire Suppression System Update: The control panel for the CO2 system has been installed, and the cylinders with gas are expected to arrive next week, bringing us closer to finalizing the fire safety measures.
3. Cabinet Installation Preparation: The server cabinets are prepped for installation. After the high-voltage tests are completed, the cabinets will be moved into the server room, allowing the next phase of the setup to proceed.
These updates reinforce our commitment to providing a state-of-the-art, eco-friendly HPC data center that supports diverse industries and advances European technological independence. We’re on track to meet our goals and look forward to sharing more progress in the coming weeks.