Operations Research Tutorial #45: Network Analysis #13_Project Optimization by Activity Crashing

preview_player
Показать описание
Watch all my Operations Research (OR) Tutorials below-

Hello friends,welcome to my new series of tutorials on Project Management using Network Analysis.
Today I'll tell you how to Optimize Project Cost and Project Duration using Activity Crashing.

This video explains-
1. Explanation of Project Management Word Problem
2. What is Predecessor Activity
3. What is Normal Project Duration and Project Cost
4. What is Crash Duration and Crash Cost - Explanation
5. Meaning of Critical Path and Critical Activities
6. How to calculate the Direct Cost,Indirect Cost,Crashing Cost and Total Cost of Project
7. How to calculate Cost Slope for critical activities
8. How to find critical cost and project completion time
9. How to reduce Project Cost - Step by Step Explanation
10. Detailed explanation of the concepts and best practices for exam
11. How to find Optimum Project Duration and Optimum Project Cost

If you like the video,please LIKE it and SHARE it. You may help someone else by spreading the knowledge!
Your small appreciation means a lot to me! Please SUBSCRIBE my channel for more videos.

I've uploaded videos on Statistics,Numerical Methods,
Business & Financial Mathematics,Operation Research,Computer Science & Engineering(CSE),Android Application Reviews,India Travel & Tourism,Street Foods,Life Tips and many other topics.

And a series of videos showing how to use your scientific calculators Casio fx-991ES & fx-82MS to do maths easily.

Join my Blog-
Рекомендации по теме
Комментарии
Автор

All Concepts of CPM, PERT and Crashing understood in less than an work....
use of examples made it easy...

Prakarc
Автор

thanx Sir for ur video it was v helpfull for me thanx a lot I tired a lot to how to crush but you made possible to understand each n every thing perfectly thanx alot

jayarajput
Автор

Really cleared my Doubts Thanks a. Lot sir!

karanmakwana
Автор

Sujoy ... u have good grab on every concept about ur subject .... hats off to that .... these videos are really helpful..!! .. try to add few questions with answers (without solution) after u complete ur lecture in video.. it will help us more for practice... thank you 

swapnilkumar
Автор

hi sir, there seems to be a mistake in calculating crashing cost. the cost of previous crashing is not considered here. crashing cost for the final step should have been rs. 600 but you took it as rs. 150. Hence total cost will be rs. 7100 and not rs. 6650. Please verify.

sirivandana
Автор

Can u also explain project crashing in which other paths also become critical simultaneously.

akshaydesai
Автор

thank you very much. u r a life saver.

SaurabhmoyLahiri
Автор

Suppose there are 3 paths in which one activity is common and crash cost is 50rs. Duration of 3 paths are 37, 36 & 34 days respectively. Do we have to crash the common activity with least cost so that duration of all paths are reduced or do we have to crash activities in such a way that duration should not be less than 34 days even if total crashing cost is higher than 50rs.? Pleas clarify the same asap.

akshaydesai
Автор

If there appears to be another critical path after the second crashing, The cost of that path will be considered and crashed too?

purvadashottar
Автор

Sir, please make videos on TRAVELLING SALESMAN PROBLEM AND BRANCH AND BOUND ALGORITHM.!
Your videos have made studying OR a delight.. its a request to make videos on these 2 topics asap.!

pjasrai
Автор

Nice video but I always ask myself how this can be applied to a large scale project where there are more thank more than 300 activities

solomonsackey
Автор

can u recommend a book for this with a lot of questions?

arjumandmahak
Автор

sir how to find free float, independent float, interfering float, slack...

dsanrame
Автор

sir plz upload a problem on game theory graphical method..

vishalkotia
Автор

for D it will be 2 days na ??? 8--6 you wrote 7 .

KumarHemjeet
Автор

I am really going mad .why aren't you crashing D directly to 6 days ???

KumarHemjeet
Автор

What if Crash Time is greater than Normal Time?

Here is the Question,
Please help me to solve it..

The data for a network is given below. Crash the network to
minimize the project duration and determine the project cost for that
duration.
Activity Normal time Normal cost Crash time Crash cost
1-2 12 85 10 140
2-3 11 95 8 160
2-4 9 110 6 170
3-4 8 120 7 160
3-5 11 70 10 100
3-6 12 65 6 90
4-5 8 75 9 90
5-6 9 90 7 130