PMBOK® Guide: Project Schedule Management- Lead and Lag

preview_player
Показать описание
Sometimes we need to either speed up the dependent activities or delay the dependent activities while keeping in the relationship as is. This is the purpose of Lead and Lag.
Lead:
Lead means ahead of time, go a little bit fast. In the case of Finish-to-Start relationship, whatever time you want to lead, you need to reduce the start time of next activity by that time. For example, in the case of 2 days as lead time in FS relationship = ST (Start time)-2 Days.

Lag: The lag time is added in the actual start date of the next activity. For example, in the case of building and painting, you say that first let me finish the product and then after a gap, I want to start painting. You need a gap of certain days before you start painting, so this is lagging time. A duration where no work is done. So leading refers to work done in parallel by 2 activities whereas lagging means giving a gap of some duration between 2 activities.

In Simple language Lead is something running ahead as speed and lag is an amount of gap introduced in between two activities.

You can explore the videos for the complete course here

The Project Management Professional (PMP), PMBOK, The Agile Certified Practitioner (PMI-ACP), and The Professional in Business Analysis (PMI-PBA) is a registered mark of the Project Management Institute, Inc.
PMBOK is a registered mark of the Project Management Institute, Inc.

Materials in this video are based on the text, A Guide to the Project Management Body of Knowledge, (PMBOK® Guide) – Sixth Edition, Project Management Institute Inc., 2017.

The PMI Registered Education Provider logo is a registered mark of the Project Management Institute, Inc.
#pmptraining #pmpexam #pmpvideos
Рекомендации по теме
Комментарии
Автор

Best PMP videos. This instructor is the absolute best. I paid a lot of money for PMP prep classes. But nothing beats this. THANK YOU!!!!

daisyduck
Автор

Hi !,
Yesterday I have cleared my PMP certification, your videos have helped me a lot. Thank you

djhnbmdjhnb
Автор

It’s takes immense courage to share the true and pure knowledge with the world.
keep sharing and imparting knowledge to aspiring and growing Project/program managers. Appreciate all your efforts.

findmaheshpatil
Автор

Great efforts done to promote knowledge best platform to learn Project management

MUHAMMAD-husn
Автор

finally, someone explained it well. Thank you!

waqarulhassan
Автор

Finaly i got what i searchedTHANK YOU SOO MUCH

mehboobalam
Автор

Wonderful explanation... Very clear.. Thank you for the content...

virginiasanchez
Автор

Leads can only be applied to activitied with finish to start.Lags on the other hand can be applied to all relationdhips.

Zahid-Raja
Автор

Clear and good explanation.
Thanks for your informative Videos.

rajneesh
Автор

I have a few questions,
is LEAD/LAG established before construction begins as in during the scheduling stage OR developed during the construction stage as its ongoing?
and if LEAD/LAG are established before construction begins, then does that mean the schedule is flawed? as in it could have been avoided by better scheduling
and could the project manager freely decide to ignore the LAG time and keep working OR ignore the LEAD time and stick to actual activity time OR is he obligated to follow LEAD/LAG?
so, does that means LEAD/LAG is superior to the actual start/finish time for each activity and the manager MUST follow it OR its optional and it just attempts to improve the schedule ?

husseinalm
Автор

Thanks for this video Sir, this has helped a lot and clear understanding between lead and Lags.

dineshkapoor
Автор

Your explanation is logical and clear. But figure 6-10 Examples of Lead and Lag in the PMBOK 6th edition is not clear and is confusing. Their examples seem to be switched for Lead and lag.

platelet
Автор

So extremely helpful. You helped me make a breakthrough.

shommytv
Автор

is this correct wrt Lead and Lag in using "painting" as the 2nd activity....for example classrooms 1, 2, 3, & 4 are to be drywalled, taped and prepped before paint but rather than start the painting activity on day 6 you want to start the painting on day 5 which means you begin painting classroom 1 & 2 while classrooms 3 & 4 are being is assuming that each classroom is being drywalled, taped and prepped for paint one at a time this classroom 1 & 2 are done by day 5...is this a good example of lead?

antoniobiancofiore
Автор

Is lead applicable to all kinds of processes? I guess it is applicable only to FS

vishwanaib
Автор

I am a bit confusing. lag time is ok. But what is the difference between fast tracking and lead time. are they similar?

mustafasatc
Автор

Sir, does duration of dependent activity changes with addition of lead & lag ??

harshadshinde
Автор

yeah lead means..leading, and lag means lagging. As clear as mud

anhtiennguyen