Project crashing full example (part 1/2)

preview_player
Показать описание
Project Management Tutorial: Project crashing full example (part 1/2).
There is an annotation that shows up at 8:39. If you are watching on a mobile device, you won't see it. It says "Sorry, I accidentally wrote TF=1 for B, I meant to write TF=1 for C... I catch this error in part two of the video." - So yes, for B, TF should be 0 and for C, TF should be 1. Also in the table of dependencies, there was a typo in the predecessors for activity E. It's predecessors should be C and D, which is what I did in the network diagram.

Please support my work:
Every dollar is seriously appreciated and enables me to continue making more tutorials
Рекомендации по теме
Комментарии
Автор

In run 2 there will be total float of 1 at C but you write it in B row correct it sir 👍

abdullahtahir
Автор

So very helpful! This and part two. I would not have gotten this right from just reading the text book.

nicholeh
Автор

Undoubtedly Best Explanation on Crashing Ever ...!! U made one small mistake while writing TF in run-2.

pratiklohar
Автор

You saved ooour life in 9 minutes -- something that the DOCTOR (or so called PhD) cannot even do! Legendary!

jasoncysiu
Автор

Thanks for the video, there is a typo in the predecessor column since the predecessor of E is also E and there is an F while there is no F as an activity.

SlimJimBigWin
Автор

Nice video very helpful....but the predecessor for activity E is C & D not E & F please correct that.

henryanda
Автор

Useful information about project crashing.Thank you

mazrimamat
Автор

quite helpful. It requires practice oftenly

clemencejacob
Автор

Can I know why you didn't choose activity c which is 400 is cheap to crash?

kavilenraaj
Автор

there is typo at 9:35, total float in table should be 0 for B and 1 for C

Feri
Автор

I just want to get this right. You said we should start crashing the activity with the lowest cost on the critical path. B= 400 and E=500. Could you please explain why you crashed E first? I a bit confused there

brahimelboudani
Автор

Very useful. I didn't know wich activity of the critical path crash first.

knifewars
Автор

in the first crash process when crashing the duration from 18 to 17, should we also remove the cost of one day from E activity so the new total cost would be 16, 900 instead of 18, 800 and do the same for the other crashes

alaamohamed-vtxq
Автор

Amazing succinct explanation. thank you

TheAbdallahalmassri
Автор

instead of overhead cost what if it said company will get x amount of reward per day if completed early? how would we amount that

dankd
Автор

Thanks for a wonderful and very clear explanation. Would like to know which tool did you use for drawing the Network Diagram.

baijumehta
Автор

Thank so much you are such a blessing, God bless you

sibusisombhele
Автор

I thought you first calculate the slope to determine which is the lowest amount to crash

joeytadayo
Автор

In Run 2 the project cost cannot be reduced as long as the duration is reduced

mohammedabdalhadi
Автор

Hello! I have problem same related to this. How can I contact you for this ? Thanks

sojanmathew