10 More Waterfall PMP Questions for a Better Life (81 to 90)

preview_player
Показать описание

To kick-start your career 🙂

You can pass your PMP Exam!

Or even just check your Project Management knowledge of waterfall projects and processes in these scenario-based watefall PMP exam questions and answers. You can do it!

Timestamps
00:00 Intro
00:33 Question 81: Project requirements
03:49 Question 82: Deliverables not accepted
06:03 Question 83: Baselining the scope
08:29 Question 84: Creating a scope statement
10:51 Question 85: What should the team work on
13:56 Question 86: Stakeholder engagement
17:27 Question 87: Impacted stakeholders
19:58 Question 88: Additional qualitative analysis
22:44 Question 89: Decision tree
25:23 Question 90: Directing PMO
27:19 I believe in you, you are amazing.

#PMP #PMBOK #projectmanagement
Рекомендации по теме
Комментарии
Автор

Yeah this was my worst one yet haha. I’m learning a lot but struggling with these a lot more than agile. I thought I knew waterfall better than agile but maybe not 😂😂

MisterStubstep
Автор

I also learned a new word also : Propinquity...and I googled it to find this : "the state of being close to someone or something; proximity". Everyday is school day like they say! 🤗🤗

b_aleeya_z
Автор

Boom, one of the hard questions i have seen yet, definitely giving a learning, thanks again @David😇

semnaresh
Автор

In q 82, why we using change control process where this is not a change its missed requirement which much be estimated earlier. If we use change control process than cost baseline will also change which is not acceptable here for project requirement. Also if defects comes before delivering the product than why change considered. It has to be addressed by team by adding in issue log.

CColorfulworlDD
Автор

Dave, this one was tough only 4 out of 10

geralde
Автор

Thank you again David, is there a playlist of those waterfall QAs as you have for Agile please? Very helpful indeed 💯❤.

b_aleeya_z
Автор

For Q82, do we not add it as an issue first then try to find the cause of the issue (perhaps do an RCA), before proceeding to discuss change.
How are we going to raise a change request if we don’t understand the cause of the defect yet or even why the requirement was missed?

anulikaabodike
Автор

Please create Playlist for PMI ACP and PMI-PBA, Business Analyst too

MrSayandeep
Автор

Thanks! Very hard but very helpful though. Are PMP exam questions are that hard & confusing like these questions?? 😣

abareglmaslooa
Автор

Hi David.. I could not find resource assignment matrix in PMBOK guide.. maybe it is responsibility assignment matrix? RACI is an example of RAM as per my knowledge.