Calculating and Understanding Schedule Variance

preview_player
Показать описание


Schedule Variance (SV) is the second of two basic variances that can be calculated once EV, PV and AC have been determined for an activity or project. SV is simply the Earned Value minus the Planned Value: SV = EV−PV
If SV is negative, that means that less work has been performed than what was planned.. If SV is positive, then more work has been done than planned. Like CV, SV can be calculated for each activity, for segments of a project (for example a deliverable or sub-deliverable) or for the entire project.
Рекомендации по теме
Комментарии
Автор

Thanks in advance for this resources, but Project total Pv is the same of Bac?

NickIlVento
Автор

To calculate SV we need EV, Please show us how to obtain EV?
thanks

arthurimmanuel