Hii...Today we going to solve an example related to program evaluation and review techniques.
Two methods of network analysis are:
Program evaluation and review techniques
Critical path method ( cpm)

In our previous video , we already discussed cpm by solving an example.

PERT Analysis. Program Evaluation and Review Technique (PERT) is a method used to examine the tasked that are in a schedule and determine a variation of the Critical Path Method (CPM). It analyzes the time required to complete each task and its associated dependencies to determine the minimum time to complete a project

In project management our topic is ......
Introduction of project management
project
Phases of project
basic terms : activities, events
common Error: looping, dangling, redundancy
Rule to draw network diagram
numbering the events : Fulkerson's rule
construction of network diagram
Time analysis: Forward pass computation
Backward pass computation
calculation of float and slack
Critical Activity
critical path
CPM (critical path method)
PERT ( program evaluation and review techniques)

THANK YOU FOR WATCHING

___________________________________________
Please like share comments and subscribe
___________________________________________

To watch more tutorial, press the below link

How to draw network diagram all basic concepts

Calculation of earliest time latest time float and critical activity

Critical Path Method ( CPM )

Travelling salesman problem

Maximization in assignment problem

Unbalanced Assignment Problem

Assignment problem for multiple solution

Assignment problem part 1

degeneracy in Transportation Problem

modi method transportation problem using north west corner rule 2

Modi Method Transportation Problem using Vam 1

unbalanced transportation problem vam method,

vogel's approximation method transportation problem

least cost method transpotation problem, unbalanced table

least cost method transportation problem, balanced table

unbalanced transportation problem using north west corner method

north-west corner method transportation problem, balanced table

transportation problem in hindi, conversion of unbalanced table into balanced table

for watch more tutorials pls visit the playlist in the channel

playlist of operation research

Playlist of Transportation Problem

playlist of probability for engineering mathematics

Playlist of Data Structure and Algorithm

My YouTube Shorts of Operation Research

Program evaluation and review techniques, program evaluation and review techniques in operation Research, program evaluation and review techniques in hindi, pert in project management in hindi, pert in hindi, pert in project management, pert in operation Research In Hindi, project evaluation technique, network analysis by pert, project evaluation method
Рекомендации по теме
Комментарии
Автор

Perfect Lecture for those who prepare for exams a day before!

its_My_officialYT
Автор

Why such teachers are not there in college ...clear explanation 💯

vh
Автор

I have got a test tomorrow in it and you just explained all of my course in just 30 minutes. Thank you very much

akvideos
Автор

I would say found your channel at the right time.
watched all of OR videos needed for my end-semester exam
A big thanks to the team

raghavbansalpec
Автор

Abhi 2 ghnte baad mera exam tha.. or ye topic clear ho gya 😂

Only_PYQs
Автор

Very well explained, thank you so much, you saved me. You were better than my IIT faculty.

armageddon
Автор

Yes
Units should be same 40 days and 36 weeks
One of these should be converted in one unit please

chandrasekharrevuru
Автор

I believe you made a mistake by comparing 40 days with 36 weeks in the last step. Please correct me if I am wrong.

s-_-r
Автор

Thnq very much ma'am..i m total Forget this ..because i read this before 3 years ago...but after watching you video i m able to remember all formulas and methods to solve PERT

prachiagrawal
Автор

Kisko kisko ye wala video muskil se mila😂

toysduniya
Автор

You're so talented and hard-working. Your way of teaching is phenomenal. Keep it up.
Best wishes for your future aspirations.

aroojqureshi
Автор

Ma'm u are a life saver for OR
Thankyou So much ✨
One of the best YouTube channel For Engineering on the Internet ♦️

zubairahmed
Автор

Expected duration was 36 weeks (roughly 252 days) and probability of completion in 40 days is 78%🙂

sahilkeshari
Автор

Luckily found your channel, well explained. Thank you so much im extremely grateful. God bless you all the best 💯

annatacouri
Автор

expected project time was in WEEKS and the probability for completing the project was 40 DAYS. that means 5.7 Weeks

rushitjain
Автор

Beautifully explained... Thanks, love from Nepal ❤️

sanjeepyadav
Автор

Unit will be either in weeks or we have to convert 36 weeks in days.. i.e (36*7) days

sudipsamrat
Автор

Ap bahut accha smjhati ho mam. Bahut help ho rhi h exam preparation me... Jo chije kbhi class me smjh ni aati h vo apke lecture me smjh aa gya. 😊😊😊thank u so much

dollysahu
Автор

Hi
I learn a lot of things from your lecturer. But I have a question
D=(Ts_Te)/sigma
Ts=40days
Te=36weeks
Is it not need for conversion of days and weeks in same units??