Variations In Construction Projects Explained

preview_player
Показать описание
In this video I walk you through variations in construction projects, including what is a variation, and the different types of variations, and also what changes in construction projects that will lead to a variation, and most importantly what are the steps to account for and execute the variations. I hope you enjoy the video
Рекомендации по теме
Комментарии
Автор

Variation means a deviation or change from the original scope of works/design/.

Variation Process

1. Notice of Variation - informs client of change stating it involves this cost impact.

2. Confirmation of Variation - Client reviews and confirms.

3. Request for Variation Order - a comparison between existing and new program of works illustrating cost for works needed. This also begs the formal amendment of existing contract.

4. Variation Order - a document like a purchase order issued by the client to the contractor to formally include works that will be financially accounted for towards the contractor.

amulabala
Автор

Thank you so much! Very useful and expecting more videos from you mentor!❤️👍🏽

mhdmushfique
Автор

Thank you so much for your sharing, sir
May I know Myanmar people can apply QS in Dubai, pls

thuthutheinaung
Автор

Hi Sir, i commented on your other video but that comment is more related to this video, Thanks for bringing me to this video link. Just a follow-up question about contract especially for variation order. First, My understanding about the calculation of variation order that it should be in detailed (same as class 1 estimate). Is it possible for a contractor to submit a variation order in a form of re-measurement? Or lumpsum?

gdfb
Автор

Hi Engr.Ahmed, as watched your another videos for IPC and to deduct 10% of retentions from every month IPC, So
for issuing variation amount to contractor, is the retention amount will also impact on variation amount or it will be fully issued to contractors? Thanks

fayazmuhammad
Автор

Thank you for the content, sir. Btw I bought your course quantity surveying on udemy but it is no longer available on the platform. Is there something wrong?

gerardodacruz
Автор

Dear Sir, EOT (the extension of time) is another form of Variation with or without a change in price of the contract. Thank you.

friendsgroup
Автор

Very nice video, add some examples with calculations also

sk-ywpz
Автор

Thank you for your videos its helpful, but i prefer to remove the music because we need to focus on the information it self no need for the sound effect .. thank u again

ayadoleh
Автор

As per the FIDIC contract, the contractor must execute the variations works even when they still haven't received the approval of their variations. Do you think that is the risk that must be accepted by contractors?

michaelnguyen
Автор

If the programme is changed by concurrently managed variations that increase value, will the cash flow forecast alter?

hendriksaldua
Автор

what about the music attached plz i cant hear you.. thank u

Toubah
Автор

Sir please add MEP measurement taking short cuys

aqtharaqadomaths
Автор

Please give example for quantity and item ??
Client wants additional door in a room ??

Is it item or quantity ???

rosiubaith
Автор

Dear Eng. Ahmad...The impact of variation on the Project Period is not explained

muhanadal-kamali