Technique for Computing Performance % Complete

preview_player
Показать описание
Primavera P6 has a setting for 'computing performance percent complete'. Does it matter how this is set? What does it do? What should you be careful about? Michael tells you everything you need to know about this setting and how to best manage it inside your project schedule.

Learn Primavera P6 as a Beginner, or become a P6 Master:

Check out our Training for Teams page to see how we can help grow your company's project controls skills:

~

TAGS:

Computing Performance % Complete, performance percent complete, % complete, Percent complete, plan academy, P6 settings, Michael lepage, free p6 help, p6 tutorial, how to calculate % complete
Рекомендации по теме
Комментарии
Автор

Our NEW Progressing Course just launched!

Check out the best Advanced P6 Training available online:

PlanAcademy
Автор

WBS milestone complete seems particularly useful when WBS entirely corresponds Bill of Quantities valued against rules of credit. In this case activities reflect the site works whilst WBS mainly contributes to valuation and financial matters.

peterwang
Автор

Imposed payment milestones should be applied in P6, on WBS level !? Could You please explain possible relationships between rules of credit and payment milestones!? Thanks

vladimirrisojevic
Автор

i have never used WBS milestone complete..i have not seen it used any schedules at all

Pacific
Автор

Please Sir, I had a question, why percentages will not roll up to project level in primavera p6, please not that it is roll up in WBS level, and I already assign recourses, please advise.

ahmadaltayeb
Автор

Hi Michael,
I have a resource - cost loaded plan, the performance % is shown zero, I have checked all the settings, could you please advise hoe to resolve the issue .
Thank you

mahansor
Автор

how to make level automatic calculatiom completed

hexiao-udzr
Автор

if WBS Milestones percent complete selected, will it change the activities Actuals automatically ?

omarmdsaleem
Автор

Excellent, I have small clarification, currently I'm working on Master schedule as vendor which contains both contractor and vendor wbs/activities. I update only vendor activities. So when I filter my vendor activities p6 is not summarizing performance %complete. Could you please help to summarize

kaviwithshanu-pursuitofper
Автор

Dear Sir,
When i update the schedule i have performance % values in activities . But in the WBS the performance % is showing as Zero. Please guide me to solve this issue. As i already refresh the schedule many times but still it is showing Zero

Aryanss
Автор

0%100% is useful for engineering activities updates, but the problem is settings is qpplied to entire schedule not to certain activity only .

khaledAhmed-ebbe